A construction permit authorises specified works. Completion records relate to the finished work, and an occupancy certificate deals with suitability for use. Ask your licensed consultant which applications cover your building and keep the latest approved drawings with each certificate. DMT construction permits. Occupancy certification decision.
Before an owner starts building
Describe the works precisely: a new building, an addition or a change to an existing structure. Provide the site details, existing approvals and proposed drawings to the consultant. Ask for the application number and approved scope before agreeing a start date. If the works move beyond the approved design, establish whether an amendment is needed before they are concealed.
DMT's Binaa platform brings authorities together for construction permitting. Confirm the route currently serving the type of project with the municipality or consultant. An owner commissioning work in a shared building should also check community approval for changes to appearance, structure or common parts. ADREC alteration rules.
At the end of construction
| Document | What it helps establish | Owner's check |
|---|
| Approved permit and drawings | The work the authority authorised | Plot, revision and scope |
| Completion certificate | Completion of the works recorded by the municipality | Correct building and issue date |
| Occupancy certificate | Suitability for occupation under the applicable system | Coverage, conditions and expiry |
Ask the project team for the final drawings, inspection outcome and outstanding items. If a floor or part of the building is still being completed, confirm exactly which part the authority has cleared. DMT's occupancy decision distinguishes initial, conditional and temporary certification. A document covering one part of a building should be read to its stated limits.
Existing buildings and renewals
DMT directed covered owners and property management companies to work with licensed engineering consultants and apply through the municipal electronic licensing system. It describes occupancy certificates as valid for up to five years depending on building and use. DMT subsequently extended the application period to 30 November 2026. Determine the position of the actual building with the municipality, including any corrective period or later decision. DMT occupancy instructions.
For a buyer, compare the approved configuration with what you are shown: an enclosed terrace, added room or division of a floor may raise a question that the original completion certificate cannot answer. Ask for the approval relating to the change. For an apartment handover, retain the building's final completion date separately from your own key collection date.
If a buyer finds an extension missing from the plan
A villa can have an original completion certificate and a later addition that does not appear on its approved drawings. Ask the owner for the permit and completion record covering the addition. Give the consultant both drawings and ask which configuration the municipality has accepted. Where records are incomplete, identify the applicable correction route before relying on the extra area in the price or mortgage valuation.
An occupancy application can also result in specific remedial work. Ask which consultant is responsible, what evidence is needed to close the findings and whether the municipality has issued an application acknowledgement or an actual certificate. Retain the issued certificate and its expiry date for the building's operational file.
Related reading includes documents to sell or rent a home, Snagging, handover and defects liability period and Strata and common-parts rules (what the service charge covers).
FAQ
Is an owner's signature on a contractor's completion sheet enough?
It records acceptance between the parties. Ask for the completion or occupancy record issued through the competent municipality.
Do all buildings have the same renewal period?
DMT states up to five years depending on building type and occupation. Use the expiry and conditions shown for the specific building.
Where do I start for a change inside an apartment?
Set out the work for the consultant and building manager. Identify any effect on structure, common services or external appearance before appointing the contractor.
Can one certificate cover an approved part of a building?
DMT's system provides for temporary occupancy in defined circumstances. Read the particular certificate, areas, dates and conditions before allowing occupation of another part.