At handover, inspect the property against the signed specification and record each defect in writing. Article 73 of Abu Dhabi's real estate sector law sets different developer liability periods for specified structural defects and defective building installations, tied to the municipal final completion certificate.
What the statutory periods cover
| Category in Article 73 | Period | Starting point |
|---|
| Defects threatening durability or safety in structural or common parts | 10 years | Date of the municipal final completion certificate |
| Repair or replacement of defective building installations | 1 year | Receipt of the municipal final completion certificate for the building |
Ask the developer for the certificate and relevant dates. Your viewing, key collection, moving date and first maintenance visit can all be different. A finishing mark, a defective fitting and a structural concern need different descriptions and may have different contractual or legal treatment. The statutory wording also preserves liability under other applicable law.
Walk the home in a repeatable order
Take the agreed plan and specification. Start at the entrance and work room by room. Open accessible doors and windows, check alignment and seals, try normal light switches and taps, and look for visible water marks or damaged finishes. Do not operate equipment that has not been commissioned. Ask the handover team to demonstrate installed systems and explain isolation points.
Give each issue a location, photograph, description and expected correction. “Water remains on the bathroom floor after normal shower use” is easier to inspect than “bathroom poor”. Record shared corridors, lifts or external walls separately and identify the management contact. For a potential safety or structural issue, report it promptly and seek an appropriate professional assessment.
Close the handover record
Ask the developer to acknowledge the list and identify who will arrange access for repairs. Mark each item as reported, inspected, repaired or awaiting a return visit. When work is said to be complete, inspect the same location under the conditions that revealed the issue. Keep before and after images and the date of acceptance.
Read the handover form before signing. Clarify what receipt of the keys acknowledges and where unresolved defects are recorded. Keep the warranty documents, equipment details, completion certificate and handover correspondence together. If a developer dispute remains, Taswea publishes a conciliation route with a jurisdiction check.
What to put in a defect report
A useful entry reads like an instruction to someone visiting the unit for the first time. Give the room, the fixture, when the problem happens and what a successful repair would look like. For intermittent water ingress, preserve images taken when the water was visible as well as a later picture of the dry surface. Ask for the inspection finding before marking the item closed.
If several units report the same fault, notify building management as well as the developer and keep the respective references. The manager may need to arrange access to a common installation while the developer assesses its responsibility. Keep those tasks separate from any insurance notification or claim for damaged belongings.
Related reading includes documents to sell or rent a home, Building permits and completion certificates for owners and Real estate dispute with a developer: where to complain.
FAQ
Does the one-year installation period start when I move in?
Article 73 links it to receipt of the building's municipal final completion certificate. Obtain the date before calculating the period.
Is every crack covered for ten years?
The statutory category involves defects threatening durability or safety. Document the location and change over time and have a qualified person assess the concern.
What if a fault recurs after a repair?
Reopen the original item, attach the earlier report and repair record, and describe the conditions under which the fault returned.
What if the handover sheet says every item is complete?
Ask to record the specific outstanding items and current condition before signing. Keep the version acknowledged by both sides. If the form's meaning is disputed, request clarification in writing before treating it as acceptance of the repairs.