Abu Dhabi's Law 3 of 2015 regulates people working in the property sector and how development projects are sold and recorded. Read it alongside Law 2 of 2025 and the implementing decisions, which changed important rules on buyer default and building management.
Before signing for a unit
Identify the company selling, the project and the specific unit. These checks answer different questions. A licensed business can have several projects, and the right on offer can be ownership or a right to use or develop land. Ask for the registered project details, the proposed plan and a contract naming the right, price, payment dates and promised unit.
The amended law requires a licence to carry on regulated real estate activities. For an off-plan purchase, DARI's first-sale registration is initiated by the developer. Its service checks include developer licences, an identified unit and a registered escrow account. Save the pre-registration certificate with the sale agreement.
Where instalments go
A project escrow account is tied to the development. Under amended Article 19, its permitted use concerns construction, completion and project finance subject to the account terms. If payment instructions change, obtain confirmation that the account belongs to the same registered project before sending an instalment. Read the current escrow provisions.
If you fall behind, act on the formal notice immediately. Amended Article 17 sets out notice, an opportunity to pay and a settlement procedure before a developer may use the statutory termination route. Keep proof of the amount paid and the date a notice arrived. The provisions preserve a buyer's recourse to court or arbitration.
From construction to occupation
The interim register records the buyer's off-plan interest. A resale before completion needs its own recorded disposition. At completion, Article 30 links final registration to the buyer meeting contractual obligations and the developer lodging the final plans. Compare the certificate against the unit and share you contracted for. Read the initial and final registration provisions.
| Stage | What to keep |
|---|
| During construction | Registered contract, instalment receipts and amendments |
| At handover | Unit inspection, final plan and completion documents |
| While owning | Registered title, management contact and approved service budget |
The amended framework uses owners' committees. The management company collects approved charges for the common parts. If an invoice or repair is disputed, identify the boundary of the unit and the relevant budget before addressing the manager. See the committee and common-property decisions.
A practical check when the project or unit changes
Suppose a developer offers a different floor plan during construction. Compare the proposed amendment with the registered unit, size, price and instalment schedule. Ask whether the change needs an amendment to the initial register, who will submit it and what document will confirm the revised entry. Keep the old and new plans with their approval dates.
If the unit later changes hands, the incoming buyer needs to know which promise is still in force. A clear sequence from the original plan to the recorded amendment is more informative than a new brochure. For a project where several buildings complete at different times, ask for the certificate and plan covering your actual building before checking final registration.
Related reading includes ADREC, DARI and Tawtheeq, Off-plan resale and assignment: rules before handover and Owners Associations / owners committees: rights and duties of unit owners.
FAQ
Which law should I quote in correspondence?
Name the relevant article of Law 3 of 2015 as amended. For a current management or default issue, read the replacement wording and the relevant implementing decision.
Does a payment receipt register my purchase?
The receipt records a payment. Ask for the registration certificate linked to the contract and check the buyer and unit identifiers.
Where do I check a property on Al Reem Island?
Al Reem and Al Maryah are within ADGM. Check the applicable registration service and rules through AccessRP.
Who do I ask if my agreement and pre-registration certificate describe different units?
Start with the developer and the competent registry. Send both documents, identify the field that differs and ask which amendment or correction is required. Keep the written answer and the corrected registration with your signed agreement.