Search the ADREC project directory by the registered project number. Open the correct phase and read its construction status and completion percentage alongside the date of the evidence. Your contractual delivery date is a separate piece of information.
Find and record the right phase
- Take the project number and phase from your sale agreement or the registration documents.
- Search Projects by number. If searching by name, narrow the results by district, developer and community.
- Open Project Details and match the project number, location, registration and building use.
- Write down the completion percentage and construction status exactly as displayed. Record when you checked and ask for the inspection date if it is missing.
An ADREC project page has separate fields for the registration date, construction status and completion percentage. The registration date can predate the latest inspection. If the public result loads with empty fields, refresh it in the service and ask the developer for the latest dated official progress evidence. An empty field does not establish zero progress.
What the inspection measures
DARI explains that developers use its project progress survey service for on-site verification and milestone-based releases under escrow financing. Buyers can ask about the underlying report and the phase it covers. The application to submit the developer’s survey is a different task from viewing the public directory.
| Item | Useful question |
|---|
| Construction percentage | Which phase was inspected, and when? |
| Contractual milestone | What document triggers my instalment? |
| Handover notice | Does it identify my unit and inspection or collection arrangements? |
When a target date changes
Compare the new written notice with the handover clause and any amendments you have agreed. Keep the source, date and phase for each change. A photograph of a finished façade can illustrate progress while leaving internal fit-out, common facilities and approvals unresolved. For Al Reem and Al Maryah, confirm the regulatory project record through ADGM.
What to request when two percentages disagree
A developer update may describe a particular tower, the structural frame or an individual package of works. The public register may show the overall percentage of a different registered phase. Write the exact label alongside each figure. Ask when each measurement was made, who verified it, which buildings it covers and whether the percentage is overall construction or one activity. Two different percentages can both be accurate observations of different work.
DARI’s survey procedure identifies a project registration certificate, site and project plans and a building permit among the developer’s supporting documents. Its workflow includes a site visit record, project photos and engineering company approval. Those are useful clues about what makes progress evidence specific. If a payment demand relies on a milestone, ask for the contractual clause and the evidence that the same phase reached it. Check them together before treating the demand as verified. Progress survey documents and workflow
Keep earlier updates when a new one arrives. A simple row for each dated observation lets you see which portion of the record changed and whether the handover target was revised at the same time. If no update has been published since your previous check, retain the last verified percentage and its date instead of estimating progress from time elapsed.
For more detail, see checking the project record, checking the developer and buying off-plan in Abu Dhabi.
FAQ
Can I turn the percentage into months until handover?
Construction stages take different amounts of time. Use the dated programme and contractual terms for timing.
What if a later phase has the same brand?
Use the phase’s project number. A percentage for a neighbouring phase can be accurate and still be irrelevant to your home.
Does 100% mean I can collect keys today?
Ask for the unit-specific handover notice, inspection arrangements and outstanding conditions. Construction progress alone does not set a collection appointment.